Determination of Incremental Buffer Based on Alternative Resource Variability

Zhang Junguang, Li Kai   

  1. School of Economics and Management, University of Science and Technology Beijing, Beijing 100083
  • Received:2016-10-19 Online:2019-03-28 Published:2019-03-27

Abstract:

To avoid the project delay caused by resource constraints at the project planning stage and the resource shortage during the project implementation, an incremental buffer sizing method based on alternative resource variability is proposed. Firstly, based on the resource-supply-risk of each critical chain activity, we determine whether or not to utilize alternative resources. Secondly, according to the resource supply risk and the alternative resource variability, we calculate the buffer size, determine the project duration and optimize the project progress network. Finally, we prove that the proposed method can improve the project schedule effectively, reduce the impact of resource risk on the project duration and improve the on-time completion rate.

Key words: critical chain, incremental buffering, resource supply risk, alternative resource variability